§ 152.006. DEADLINE FOR ACTIONS.  


Latest version.
  • It is the intent of the city to comply with state requirements for timely review and actions requiring formal approval by the city. Information submissions and applications must be determined by the city to be complete before a timeline for action is initiated. The review for completeness will be conducted within ten business days of receipt of an application. In the event the city cannot act upon a request within a timeframe of 60 days, the city will notify an applicant in writing that action will be completed within 120 days of the date the application was accepted by the city. In the event that multiple approvals are involved in any action, such as a site plan review requiring a variance or a zoning ordinance amendment requiring a Comprehensive Plan amendment, each action shall require a separate, independent timeline for action.
    (Ord. 102, passed 7-9-01)